Survey work for MMTS up to Yadadri going on

South Central Railway General Manager Vinod Kumar Yadav has made it clear that the survey works for MMTS up to Yadagirigutta were going on and tenders will be called upon in April. He said that the works will be launched in October or November. After examining the MMTS phase-II works at field level in the Secunderabad-Moulali-Ghatkesar route, Yadav said that the works of Tellapur-Ramachandrapuram line in MMTS phase-II will be started in December. The second phase works will be completed by 2018, he said and explained that the department was discussing with the Civil Aviation Department officials on the hurdles in extending the MMTS up to Shamshabad Airport. Yadav also informed that new terminal will be constructed at Charlapally.